Energy giant completes installation of monopile foundations

Dezember 2025 | Redaktion

Energy company RWE has completed the installation of all monopile foundations for the wind turbines of the offshore wind farm Nordseecluster A . In total, 44 turbine foundations – each approximately 85m long and weighing around 1,500 tonnes – were installed at sea. Before installation, the foundations were temporarily stored in Eemshaven, the Netherlands, and transported to the construction site by Van Oord’s installation vessels Boreas and Aeolus . Instead of separate transition pieces, extended single monopiles were used, equipped with secondary steel structures such as access ladders and foundation working platforms....